Welcome to the Setchell Estate underground mains project's Project Updates page.

Take a look below to find:

  • Latest updates and progress reports
  • News direct from site
  • Milestone achievements
  • Advanced service warnings
  • Emergency contact details for site based issues
  • Historic newsletters for download

Latest News: Underground Burst on Hazel way

25/08/2026

Footage below was captured by OCO LTD operatives on site, showing the extent of the burst.

As of the AM 26/08/2026, a temporary repair is being performed.

Should the below video not load, you can watch here

Phases

Phases overview

Project Updates

5 August 2026 14:00 - No end date

Project Update:

Underground Burst - Hazel Way

On the 24/08/2026, LBS were made aware of a potential underground leak affecting the area of Hazel Way.

OCO LTD were dispatched to site to investigate and locate where the issue was originating from.

After extensive surveys, OCO LTD were able to locate the area of pipework which had burst. OCO LTD will remain on site until a suitable repair can be instigated. The extent of the underground burst can be witnessed in the below video, taken by operatives on site:





Residents experiencing a drop in service within properties along Hazel Way are encouraged to report the issue to Southwark Council's contact centre.


Further updates to follow.


London Borough of Southwark & TDC on site.

On 29th of July 2026, engineers from Southwark Council, our design consultants (TDC) and specialist contractor (OCO Ltd) visited the estate to review the proposed route for the new underground pipework. This visit helped us to identify any potential issues before the work begins.

We'd like to thank the residents who kindly allowed access to their homes . Your support is helping us plan the works carefully and reduce disruption wherever possible.