Welcome to the North Peckham boiler house refurbishment project

The London Borough of Southwark is committed to upgrading the existing heating networks to bring comfort and stability to their residents.

The refurbishment of the North Peckham boiler house aims to provide a reliable and efficient heating and hot water service.

Additionally, the long-term goal is to connect this unit to the SELCHP system operated by VEOLIA.

This will be an exciting next step for Southwark's goal to be a greener more carbon neutral borough.

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.

Phases

Phases overview
North Peckham Boiler House
Latest News
Notice Board
Estimated Timeline of Works

Estimated Timeline of Works

4 March 2024 - No end date

Estimated Timeline of Works:


Start Dates:

Project start date 5th of June 2023

-- --

Mobilisation & Initial Site Surveys:

Site surveys conducted from the 5th of June until the 30th June.

-- --

Boiler Manufacture:

Start dates: From June till September (2023)

-- --

Boiler Room Strip Out:

Strip out commencing in July until end of August (2023)

-- --

Boiler Removal From Site:

Boiler removal start date in July till end of July. (2023)

-- --

Plant Room Preparation:

Preparation starting date 1st September till end of October. (2023)

-- --

Boiler Transportation:

Start date: Last week of October (2023)

-- --

Boiler Delivery & Positioning:

Boilers will be delivered to site

Start date: End of October - 1st week of November (2023)

-- --

Road Closures & Crane Attendance:

Road closures will be essential for boiler delivery.

1st of November - 3rd November (2023)

-- --

Internal Installations:

Boiler room installation such as pipes, lights, BMS.

Start date: October until end of project.

-- --

Completion date:

Project completion date forecasted for May (2025) Subject to change due to electrical works and EICR testing. << We are here.

-- --

Completion announcement:

----